Built Robotics RPD 35

Autonomous pile driver built on a Caterpillar 335 excavator with a Rammer vibratory hammer, which drives the steel piles of solar trackers on utility-scale PV plants. Built Robotics unveiled it in March 2023; per the maker it combines surveying, pile distribution, pile driving and as-built records, and it always works paired with the RPS 25 robotic pile stabilizer. In the Goorambat East pilot (Australia) it installed 1,723 piles between February and April 2025 but, according to the contractor, at a slower rate than a conventional crew.

Year
2023
Origin
United States
Autonomy
L3 · Conditional autonomy
Dataset review
2026-11 · Methodology & evidence levels

What it does, and on what evidence

Five mandatory fields on every sheet. A product page proves neither commercial availability nor full autonomy: here we separate what has been documented from what is announced.

1 · Task
Drive, in the planned order, the steel H-piles that support the tracker structures of a solar plant, from a pile plan with the GPS coordinates of each pile top, and document each installed pile.
2 · Autonomy by task

Does on its own

Inside a geofenced work zone it positions itself with RTK GPS, picks the right pile type from its baskets, places it in the chute and drives it by vibration; it flags piles that hit refusal and moves on, and it produces as-built drawings. The RPS 25, a second machine on a Caterpillar 325 with RTK GPS and LiDAR, locates and holds each pile to meet plumbness, twist and height. If its AI cameras detect a person nearby, it stops autonomous operation.

A person steps in

People load piles into baskets with a mini excavator and the baskets onto the machine with a telehandler before each run; they set up the geofence and physical barrier, and refusal criteria are calibrated to the ground. Operators trained by Built (or Built employees) supervise it remotely with the Everest and Guardian software, can control it remotely and have wireless emergency stops. In the 2025 pilot, manual pile loading was the main human task, every pile position was surveyed by hand as a site requirement and there was downtime for maintenance.[Built Robotics][Built Robotics, 2026][ARENA, 2025][RenewEconomy, 2025]

3 · Strongest evidence

Pilot2025-04

5 MW pilot at ENGIE's Goorambat East solar farm (Victoria, Australia), with Bouygues Construction Australia and Equans as contractors and ARENA support: the first-generation system installed 1,723 piles between 24 February and 1 April 2025 with zero safety incidents, and according to the manual measurements Built reports the typical deviations stayed within the minimum required tolerances. Bouygues' project director reported 120 piles a day versus over 250 with the traditional method. The maker advertises 1–3 min cycles per pile (2–5 min manually), “up to 5×” faster and, in 2023, over 300 piles a day with a two-person crew, figures not demonstrated in that pilot.[ARENA, 2025][RenewEconomy, 2025][Built Robotics][The Robot Report, 2023]

4 · Access
Commercial product

Offered as robot-as-a-service (RaaS), priced per pile for each project (not published) and with minimum deployment lengths; United States and Australia only. The customer provides the mini excavator and telehandler for loading.

5 · Lifecycle
Current generation

Built calls the 2025 pilot system “Gen 1” and announced a second generation (concept prototype) that will carry standard pile bundles. In October 2026 ARENA committed up to A$13.3 million for Built Robotics Australia to manufacture and deploy 12 robotic piling systems in Brisbane.

[Built Robotics][ARENA, 2025][ARENA, 2026]

Spec sheet

Manufacturer maxima under declared conditions; not simultaneous. The test condition is shown under each value.

Weight
65.32 t
fully loaded operating weight (144,000 lb) on a Caterpillar 335 base excavator; ground pressure of 11 psi (about 76 kPa)
Payload
18,144 kg
maximum payload of the pile sleds (40,000 lb), up to 224 piles depending on type. The 2026 spec sheet supports 9 to 20 ft piles up to 1,000 lb (W6, W8 and W10 sections); the web page gives 10–19 ft, 600 lb and W6×7 to W8×28
Operating time
Not published

Primary source quality: Manufacturer / operator

Backed by:[Built Robotics, 2026][Built Robotics]

Taxonomy profile

Where the platform sits on the four axes of the reference framework.

Autonomy

Conditional autonomy
  1. L0
  2. L1
  3. L2
  4. L3
  5. L4
  6. L5

Makes local decisions on unexpected events; needs occasional remote supervision.

Coordination

Coordinated
  1. Standalone
  2. Coordinated
  3. Collaborative swarm

Shares state and telemetry through a base station or central server.

Control

primary: Supervised mission
  1. FPV
  2. Teleop
  3. Supervised
  4. BVLOS
  5. RL/VLA

supported: Teleoperation · Supervised mission

Perception

3 sensing modalities
  • GNSS / RTK
  • IMU
  • RGB cameras

Operating environments

  • Construction site

Sectors

  • Construction
  • Energy

Ideal business case

Pile driving on utility-scale solar farms